The Challenge

Snap was awarded the opportunity to install a dvLED wall and a 55" SOC screen (not pictured) in the lobby of a corporate downtown bank location. While dvLED video walls have different installation requirements than other display options, the modules fit together like building blocks.

Snap and team were asked to pick-up, load and transport the product to site prior to the day(s) of install.

 

 

Our Solution

It is crucial to take precise measurements to ensure accurate install and to shorten overall process. Luckily, there were no setbacks, complications or delays, despite missing product on site which was quickly resolved before the project began.

With the help of our partner's lead project team, the install was completed within an impressive two day time frame, done by one Snap service provider.