The Challenge
Snap was asked to work closely with a partner to help setup a large-scale IP-over-TV installation. The installation was for over 250 screens at one location, the NFL Hall of Fame Stadium in Canton, OH. This large-scale project had a start date of mid-July and a deadline of late August due to the scheduled NFL Hall of Fame Game.
Additionally the site was under full construction, which resulted in different variances in installation and required custom mounting procedures. Beyond the installation, the site posed many logistical challenges with product staging and availability.
Our Solution
The logistic and installation issues were mitigated by Snap’s project management team through daily progress checkpoints, design-mounted solution assistance, and daily schedules with the warehouses. Additional labor was also brought to complete the installation prior to kick-off.